FM 101-10 Staff Officers Field Manual Organization Technical Logistical Data (1941), p. 125

Page 125 of 363 in FM 101-10

Transcription

52-53 TROOP MOVEMENTS 6. A march graph is the simplest method of obtaining data required for a march table or order. It shows the approximate location at any hour of the head or tail of each serial, providing the march proceeds as scheduled. The march graph is prepared on cross-section paper, using one sheet for each route. The vertical scale to the left, with point of origin at the bottom, serves as a distance scale in miles and should show the relative locations along the route of critical points where coordination of the movement is required. The horizontal scale provides a time scale in hours, beginning at the left with the earliest hour at which the first serial may start the march. c. A serial is represented on the graph by a horizontal line, drawn to scale, equal to the time-length of the serial. This line is plotted opposite the point on the vertical scale, corresponding to the initial point of the serial; the left of the line being plotted above the hour, on the horizontal scale, at which the serial begins the march. From this left end a line is drawn upward at a slope representing the rate of march (at 10 miles per hour the slope equals 10 miles on the vertical to 1 hour on the horizontal scale). This sloping line represents the march of the head of the column. The intersection of this line with the horizontal line from any point along the route, if projected down to the time scale, will show the time the head ar rives at such point. A line drawn from the right end of the horizontal line representing the time-length of the serial and parallel to the line represent ing the head of the column will represent the tail of the serial. Time of clearances may be obtained as explained for the head of the serial. The movement or location of a unit after it leaves the route represented on the distance scale, or passes the rear boundary of its destination (new bivouac area), may be shown on the graph by dotted lines. d. If the hour at which a march must be completed is the only time factor known, the graph may be constructed starting with the tail of the column at the destination and working back to obtain the hour of starting for the head of the column. The graphs of all serials may be adjusted to al low for crossing columns or other interferences. The need for and the means of making such adjustments may be visualized. In preparing the march graph a safety factor of 15 to 30 minutes should be allowed between serials at critical points on the route. In the march table this time is divided be tween serials, the major portion usually being assigned to the leading serial. A small gap of about 5 minutes should be reserved during which the route is clear. • 53. EXAMPLES op MARCH GRAPHS AND MARCH TABLES.—a. The division commander has directed that the 1st Engr Bn, 1st QM Bn, 1st Med Bn, and the 1st Infantry, in army reserve, move under cover of darkness from their present bivouacs, areas A and B to areas C and D, beginning at 7:00 PM, 17 October 19_, under the following conditions. 120

Uncorrected OCR text. Columns and tables may be out of order; the scan is the authority.

Original scan

Loading the original scan…
Original scan, PDF page 125. Only this page is downloaded. Open the full PDF

FM 101-10 Staff Officers Field Manual Organization Technical Logistical Data, PDF page 125

100%

Data on this page

4 data points

AttributeValue
US march graph method
safety factor allowed between serials at critical points15-30 minutes“In preparing the march graph a safety factor of 15 to 30 minutes should be allowed between serials”
clear gap reserved during which route is clear5 minutes“A small gap of about 5 minutes should be reserved”
example march rate for slope of head of column10 miles per hour“at 10 miles per hour the slope equals 10 miles on the vertical to 1 hour”
US division march, example march graph / table
start hour of example movement7:00 PM“beginning at 7:00 PM, 17 October 19_”