FIELD ENGINEERING DATA 193-194 Blade grader, 7^-ton—440 sq yds gravel road surface scar- (self-propelled) ified and reshaped per hour. —50 cu yds of loose rock or loose earth spread per hour. NOTE (1) Planks running lengthwise of road on each tread. 194. BRIDGE AND FERRYING EQUIPMENT.—a. Distribution of equipment. 1 Engineer Battalion, Combat, Triangular Division (T/O 5-75)............— ........... Engineer Squadron, Cavalry Division (T/O 5-115).......... Engineer Regiment, Combat, Square Division (T/O 5-11) Engineer Regiment, Combat, Corps (T/O 5-171).............. Engineer Company, Bridge, Armored Division (T/O 5-215) Engineer Company, Light Ponton (T/O 5-85).............. Engineer Battalion, Heavy Ponton (T/O 5-275)............ 2 Assault boats 10 10 20 30 20 80 3 Ferry •units (30- ton) 2 4 Foot bridge, M-1938 (units of JtSS feet) 1 2 6 Light ponton bridge (10-ton), M-1938 (units of 850 feet) 3© 6 Heavy ponton bridge (26-ton), M-1940 (units of 250 feet) 1 4® 7 8 9 Fixed bridges Portable steel bridge, H-10 capacity ® (feet) 72 Portable steel bridge, H-SO capacity ® (feet) 125 Portable trestle bridge (feet) 300 NOTES © Also stocked in Corps and Army depots. © Will provide approximately 350 feet of reinforced bridge (20-ton capacity). ® Will provide approximately 430 feet of reinforced bridge (50-ton capacity). 275

Uncorrected OCR text. Columns and tables may be out of order; the scan is the authority.

Original scan

Loading the original scan…
Original scan, PDF page 280. Only this page is downloaded. Open the full PDF

FM 101-10 Staff Officers Field Manual Organization Technical Logistical Data, PDF page 280

100%

Data on this page

13 data points

AttributeValue
engineer battalion, combat, triangular division (T/O 5-75)
assault boats10 boats“10 10 20 30 20 80”
engineer squadron, cavalry division (T/O 5-115)
assault boats10 boats“10 10 20 30 20 80”
engineer regiment, combat, square division (T/O 5-11)
assault boats20 boats“10 10 20 30 20 80”
engineer regiment, combat, corps (T/O 5-171)
assault boats30 boats“10 10 20 30 20 80”
engineer company, bridge, armored division (T/O 5-215)
assault boats20 boats“10 10 20 30 20 80”
engineer company, light ponton (T/O 5-85)
assault boats80 boats“10 10 20 30 20 80”
light ponton bridge, 10-ton, M-1938
unit length850 feet“M-1938 (units of 850 feet)”
heavy ponton bridge, 26-ton, M-1940
unit length250 feet“Heavy ponton bridge (26-ton), M-1940 (units of 250 feet)”
portable steel bridge, H-10 capacity
bridge length72 feet“H-10 capacity ® (feet) 72”
portable steel bridge, H-20 capacity
bridge length125 feet“capacity ® (feet) 125”
portable trestle bridge
bridge length300 feet“trestle bridge (feet) 300”
reinforced bridge provided by 20-ton-capacity bridge stock
length provided350 feet“Will provide approximately 350 feet of reinforced bridge (20-ton capacity).”
reinforced bridge provided by 50-ton-capacity bridge stock
length provided430 feet“Will provide approximately 430 feet of reinforced bridge (50-ton capacity).”

Extracted from this page by machine. Each row quotes the text it came from; check it against the scan.