FM 101-10 Staff Officers Field Manual Organization Technical Logistical Data (1941), p. 279

Page 279 of 363 in FM 101-10

Transcription

193 FIELD ENGINEERING DATA \. (1) Labor for repair of road craters. Method of repair Man-hours required Earth fill with shovels alone Earth fill with shovels and trucks where hauling distance is not over 200 yards and number of trucks is Vt number of men Spaned with standard bridge trestle and bents (trained workmen) Spanned with timber bridge (trees in vicinity, trained workmen) Detour of corduroy (corduroy available in vicinity) ———————————————________Detour of planks _————______________ 4 x volume in cubic yards 2 x volume In cubic yards 15 x diameter in yards 60 x diameter in yards 18 x diameter in yards 9 x diameter in yards __ NOTES (1) The volume of a conical road crater is V = 7f TO——iti where V = volume of crater in cubic yards. D = distance across top of crater in yards, d = depth of crater in yards. IT = 3.1416. (2) A rough rule of thumb is: Fill craters under 7 yards in diameter. Bridge or detour craters over 7 yards in diameter. (2) Data for rough estimates of road work. (a) Clearing and grubbing with hand tools, medium clearing, 40 feet width, 55—140 man-hours per 100 linear yards. (b) Earth handling with hand tools, Excavation in average soil with pick and shovel 0-6 feet deep —1 cu yd per man-hour. Loading average soil into trucks, using shovel in loose soil— 2 cu yds per man-hour. (c) Materials required for plank-tread road u) for motor transporta tion—12 tons lumber and spikes per 100 linear yds. (d) Materials required for one-track plank road for motor transporta tion—35 tons lumber and spikes per 100 linear yds. (e) Average weight of lumber is 40 pounds per cubic foot. (f) Materials needed for 10 foot width of crushed stone or gravel roads: 4" depth spread—37 cu yds per 100 lin yd, 650 cu yds per mile. 8" depth spread—74 cu yds per 100 lin yd, 1300 cu yds per mile. 1 cu yd of crushed stone weighs approximately 1^ tons, or is a light load for a 1%-T truck. (g) Capacity of road-construction equipment: % yard power shovel—24 cu yds per hour, average soil, good operator. Bulldozer, 60 HP—50 cu yds per hour on level, 100 ft haul. 274

Uncorrected OCR text. Columns and tables may be out of order; the scan is the authority.

Original scan

Loading the original scan…
Original scan, PDF page 279. Only this page is downloaded. Open the full PDF

FM 101-10 Staff Officers Field Manual Organization Technical Logistical Data, PDF page 279

100%

Data on this page

23 data points

AttributeValue
road crater repair, earth fill with shovels and trucks
man-hours per cubic yard of crater volume2 man-hours per cu yd“is not over 200 yards and number of trucks”
maximum hauling distance200 yards“is not over 200 yards and number of trucks”
road crater repair, standard bridge trestle and bents
man-hours per yard of crater diameter15 man-hours per yd“15 x diameter in yards”
road crater repair, timber bridge
man-hours per yard of crater diameter60 man-hours per yd“60 x diameter in yards”
road crater repair, corduroy detour
man-hours per yard of crater diameter18 man-hours per yd“18 x diameter in yards”
road crater repair, plank detour
man-hours per yard of crater diameter9 man-hours per yd“9 x diameter in yards”
road crater fill-or-bridge threshold
crater diameter below which to fill7 yards“Fill craters under 7 yards in diameter.”
road crater bridge-or-detour threshold
crater diameter above which to bridge or detour7 yards“Bridge or detour craters over 7 yards in diameter.”
road clearing with hand tools, medium clearing
labor per 100 linear yards, low55 man-hours per 100 linear yd“40 feet width, 55—140 man-hours per 100 linear yards.”
labor per 100 linear yards, high140 man-hours per 100 linear yd“40 feet width, 55—140 man-hours per 100 linear yards.”
road clearing with hand tools
clearing width40 feet“40 feet width, 55—140 man-hours per 100 linear yards.”
earth excavation, pick and shovel
rate1 cu yd per man-hour“1 cu yd per man-hour.”
loading average soil into trucks by shovel
rate2 cu yd per man-hour“loose soil— 2 cu yds per man-hour.”
plank-tread road for motor transport
lumber and spikes12 tons per 100 linear yd“12 tons lumber and spikes per 100 linear yds.”
one-track plank road for motor transport
lumber and spikes35 tons per 100 linear yd“35 tons lumber and spikes per 100 linear yds.”
lumber
average weight40 pounds per cubic foot“Average weight of lumber is 40 pounds per cubic foot.”
crushed stone or gravel road, 10-ft width, 4-inch depth
material per 100 linear yd37 cu yd per 100 linear yd“depth spread—37 cu yds per 100 lin yd, 650 cu yds per”
material per mile650 cu yd per mile“100 lin yd, 650 cu yds per”
crushed stone or gravel road, 10-ft width, 8-inch depth
material per 100 linear yd74 cu yd per 100 linear yd“depth spread—74 cu yds per 100 lin yd, 1300 cu yds per”
material per mile1300 cu yd per mile“depth spread—74 cu yds per 100 lin yd, 1300 cu yds per”
power shovel 3/4 yd
output24 cu yd per hour“power shovel—24 cu yds per hour, average soil, good”
bulldozer 60 HP
output50 cu yd per hour“Bulldozer, 60 HP—50 cu yds per hour on level, 100 ft haul.”
haul distance100 feet“Bulldozer, 60 HP—50 cu yds per hour on level, 100 ft haul.”